Here's the official construction schedule for the new bridge!

Construction begins: March 8, 2016 (preliminary work began in February 2016)

New bridge scheduled to open to traffic: November 2018

Demolition of existing bridge: November 2018–September 2019

Project scheduled to be completed: September 2019

The bridge is designed and constructed in five different zones. Construction will start at the south end approach, north end approach and navigation. Once the north and south approaches are completed, work will begin on the sections that will connect each end with the navigation zone (the high rise).